Tons placed as the yardstick for a base job
Base work is sold by the area but costs by the ton. Every ton is bought at the pit, hauled, spread and compacted, and the hours follow the loads. That is why the calculator counts tons: 561 tons on the example lot, which is 408 cubic yards of compacted base 6 inches deep.
Convert yards to tons before you price, never after. The pit sells by the ton, the trucks carry tons, and a bid built on yards comes up short by the difference. For a check against the area, the example works out to about $1.08 a square foot of finished lot.
Loader, dump truck and trailer: the $3,576 machine line
The machine line is the number that separates an excavation bid from a labour bid. In the example the compact track loader grades, spreads and compacts for 55 hours, the dump truck hauls for 38 the pickup and trailer move the loader in, and the laser level checks grade. At each machine's own cost per running hour, that comes to $3,576.
Leave it out and the lot drops to $19,548.59, which still looks like a fair price and quietly gives away $4,291.20 of machine wear, fuel and payments. Keep the machines out of the labour rate and in this box, so a job with the big excavator and one with just the loader get priced differently. The overhead and profit guide explains where the rest of the yard costs go.
A pit 30 minutes farther away
Haul distance changes the bid more than the size of the lot. If the pit is farther and the 37 loads take 19 more hours in total, the crew hours go from 132.96 to 152.03 and the truck runs 19 more hours, about $879 more of machine time:
| Same 561-ton lot | Crew hours | Machine line | Bid | Per ton |
|---|---|---|---|---|
| Example pit | 132.96 | $3,576 | $23,839.79 | $42.50 |
| Pit farther out | 152.03 | $4,455 | $26,428.14 | $47.11 |
Two contractors bidding the same lot can be $2,588.35 apart for this reason alone. Price from your own pit, not from the number the other outfit gave.
What the excavation spreadsheet adds to reach $26,433
Operator time is priced here at $67 an hour, the example dirt outfit's break-even before any machine cost. Your shop, wages and insurance set yours, so run them through the hourly rate tool before you bid off this page.
The spreadsheet then lists each machine with its own payment, upkeep and yearly hours, adds a cushion for the last 10% of grading that always takes longer, waste on the stone, and the trip to load and haul the machine home at the end. It also prints a customer quote with your terms for soft spots and extra fabric, and logs actual hours against the bid. That is why its version of the same lot comes to $26,433 instead of $23,839.79. The excavation pricing guide walks through that bid.