Drywall Pricing Calculator: Bid Hang and Finish by the Board Foot

Updated

A 3,488 board ft basement, hung, taped and finished smooth at 78.13 crew hours, comes to $8,038.73, or $2.30 a board foot, at a $60 break-even rate with 13% profit. Change the yellow boxes to your own job and the bid updates as you type.

This drywall pricing calculator prices hang and finish from board feet, crew hours per board foot and what you spend on board, mud and bead. The starting numbers are a simplified version of the basement finish in the Drywall Pricing Calculator spreadsheet, so you see a real bid before you enter yours.

1. The job
board ft

A 4x12 sheet is 48 board ft, a 4x8 is 32.

hrs

0.0224 is 2.24 hours per 100 board ft: hang, tape, three coats, sand, every person added up.

$

Everything you buy for the job, divided by the board feet.

2. Costs that come with every job

The ones owners leave out most. Put 0 if it doesn't apply.

$
$
$
3. Your rate and profit
$/hr

What each labour hour has to bring in to cover wages and overhead.

%
%

Don't know your break-even rate? Work it out in two minutes with the true hourly rate calculator.

Job price$8,039

Counting board feet from the sheets you hang

Board feet are the sheet faces you hang, not the floor area of the room. Count sheets by size, multiply, and add them up. The example basement is 62 regular 4x12 sheets, 8 fire-rated 4x12s by the mechanical room and 4 moisture-resistant 4x8s, which is 3,488 board ft.

Use the real wall heights, not the plans. A basement with 8 ft 6 in walls needs a rip strip on every wall, and that cut, carried, screwed and taped strip is labour the plan never shows. Count it as board feet and give it hours.

Hang, tape, three coats and sand: hours per 100 board feet

The labour box reads 0.0224 crew hours a board foot, which is easier to think about as 2.24 hours per 100 board feet. That covers checking backing, hanging ceilings and walls, corner bead and tape, three coats, sanding with dust control and the touch-up walk. It also covers each trip to the site, because a three-coat finish means coming back on several days.

The finish level moves this number most. If a skim coat over everything lifts it to 0.028, the basement goes from $8,038.73 to $9,363.05, or $2.68 a board foot. Bid a smoother finish at the standard number and you put on that coat for nothing.

A 500 board ft room next to the 3,488 board ft basement

Board delivery, the dump fee and the mud, blades and screws you use up total $260 and come with every job. Small rooms carry them over fewer feet:

Job Crew hours Bid Per board ft
100 board ft patch 2.24 $515.84 $5.16
500 board ft room 11.2 $1,404.02 $2.81
1,200 board ft addition 26.88 $2,958.34 $2.47
3,488 board ft basement, example 78.13 $8,038.73 $2.30

A patch still means a drive, unloading tools and three return trips for coats. On a real patch, drop the delivery box, raise the hours, and watch the $400 minimum.

What the drywall spreadsheet adds to reach $9,646

Those bids all lean on $60 an hour, the example hang-and-tape shop's break-even. A two-person shop with one truck will land somewhere else, so get your number from the break-even hourly rate tool. At 13% profit on cost the example keeps a thin margin, which the markup vs margin guide explains.

The spreadsheet then charges the truck, lift, stilts and sander by their running hours, adds waste on board, a small cushion, the time spent on the estimate and protecting the floors, and lists each material from a price list. It prints a customer quote with your terms on bad framing and other trades' damage, and logs whether the job made money. That is why its version of the basement is $9,646 instead of $8,038.73. The drywall pricing guide walks through that bid.

How the math in the Drywall Contractor calculator is checked

Every version of the drywall contractor spreadsheet goes through an automatic test before it ships. The test rebuilds the file, recalculates it in a separate spreadsheet engine, and fails the release if any of these is off.

  • The example's break-even rate, $60.30 an hour, is worked out a second time outside the spreadsheet and the two have to agree to the cent.
  • The total for the customer has to equal the price plus sales tax, and the customer quote has to show that same total.
  • The example quote ($9,646 total) has to earn more per labour hour than it costs to run the business. It earns $81.88 an hour against the $60.30 break-even.
  • Then the test tries to break it: every yellow box on the quote emptied, nobody on the crew billable, a material price 400 days old, an order of zero. No cell may show an error, and the checks box has to flag the missing customer name and the out-of-date price.
  • The formulas only use functions that work the same way in Excel and Google Sheets.

Last test run: Drywall Contractor passed, along with 39 of the other 39 trades. The example job and the list of easy-to-miss costs come from research into 9 videos of drywall contractor owners explaining how they price. More on how the calculators are built.

Questions owners ask

How do I use a drywall pricing calculator to bid a basement?

Enter the board feet, your crew hours per board foot and your material cost per board foot, then delivery and dump costs, your break-even rate, markup and profit. The 3,488 board ft example basement comes to $8,038.73, or $2.30 a board foot.

How many hours does it take to hang and finish 1,000 board feet?

About 22.4 crew hours in the example, counting hanging, taping, three coats, sanding and the trips between coats. High ceilings, lots of corners or a smoother finish push it up.

Why does a one-room drywall job cost more per board foot?

Because delivery, the dump fee and the opened buckets cost the same on a small job. In this calculator a 500 board ft room comes to $2.81 a board foot against $2.30 for the basement.

How do I count board feet for a drywall bid?

Count the sheets you will hang and multiply by their size: 48 for a 4x12, 32 for a 4x8. The example basement is 62 regular and 8 fire-rated 4x12 sheets plus 4 moisture-resistant 4x8s, which is 3,488 board ft.